SITUATION:
BOND was chosen to furnish and install the natural gas supply point for the new Towantic Energy Center. The scope of work included the procurement and installation of a 1,300 SF precast concrete building, meter station assembly, filter separator, 1,000 feet of 16″ gas main, controls system, pressure test, gas main tie-in and all associated valves and equipment.
CHALLENGES:
- Project required a Critical Path Method (CPM) schedule
- Delivery of a complete project data book
- Strict quality control measures needed for installed instrumentation
SOLUTIONS:
- Weekly project and client team meetings to monitor project progression
- Implemented reoccurring daily and weekly tasks that organized project work in a data book format
- Developed course of action to resolve any issues and schedule adjustments
RESULTS:
- Scheduled milestones were met and project was completed early
- Delivered project data book to client in digital and hardcopy form that was thorough, organized and detailed
- Successfully tied in project with no disruption to existing gas facilities and power plant construction